2019 Resurfacing Schedule

The City of Canfield will begin our 2019 Resurfacing project the week of September 3rd, and will proceed for approximately two weeks.

We have coordinated with the contractor to perform the work outside of the busy school rush hours in the morning and afternoons.

Please remember to use caution when driving these streets as crews will be working.

9/3/2019 – Scott Street > Edwards > Cardinal

9/4/2019 – Southview > Brookpark > Deer Trail

9/5/2019 – Sawmill Run

9/6/2019 – Talsman